« USDOT Innovation Grant: Medford I-93 Bridge Project | Main | Federal Innovation Grant Boosts Charlemont Project »

March 10, 2011

Comments

A.B.

How long will the prep work last and will people be notified 24 hours in advance if a road below the bridge will have to be closed, such as Webster street, Salem street or valley street?
---------------------------------------------------------------------------
The prep work will continue until actual weekend heavy construction begins in June. We will provide updates each week and more often as necessary regarding all street and lane restrictions. Thanks.

Dan

Can you give us more info on how you intend to achieve this fast turnaround. Are you building the bridges to the side then sliding them over like you did on Rt2? Or are you using some other method?
----------------------------------------------------------------------------
Thank you for your interest in the 93 Fast 14 project. You posed an excellent question.

By using innovative construction practices, we will be able to complete this project much more quickly than we could if we were to use conventional construction methods. In order to accomplish this, MassDOT’s contractor will replace each existing bridge superstructure (concrete deck and steel beams) with several modular bridge units which will be fabricated off-site and trucked in for the project. Each modular bridge unit will be made of a concrete deck on top of two steel beams, called stringers. When they arrive on-site they will be ready to be put in place by crane. Crews will erect the replacement superstructure by hoisting and lowering each modular unit into place. There will be gaps between each modular unit. Once the units are in their final location, crews will pour a special concrete mix in the gaps between units. Since it closes the gaps, this connecting concrete is referred to as a ‘closure pour’. The concrete mix crews will use for the closure pour has been specially designed to cure rapidly. Once the concrete cures, crews will paint temporary lane markings and install a barrier system. The bridge will then be ready to be reopened for vehicular use.

Crews will be performing other preparatory and finish work outside of the weekend bridge replacement work hours. Such work includes preparing the bridge seats for the modular units, substructure repairs, surveying, and utility work. Finish work will include installation of parapet walls, paving, and final line striping.

In comparison, conventional construction methods would necessitate long-term lane closures. Work would occur on one lane at a time. The bridge superstructures would be demolished and replaced piece-by-piece with cast-in-place concrete. It would take at least four years to complete this work using conventional construction methods. By using accelerated bridge construction techniques, the bridges will be completed in a single construction season. Although the use of prefabricated modular bridge units is innovative, it is a proven technology that has been used to rapidly replace bridges in many locations across the country.

This project is part of the Accelerated Bridge Program, which serves as MassDOT’s ‘laboratory of innovation’. The Accelerated Bridge Program is implementing several cutting-edge bridge construction technologies in order to improve Massachusetts’ infrastructure rapidly, safely, and efficiently while causing the least possible construction-related impacts to road users and communities.

The comments to this entry are closed.

  • feedback button

Photo album